Construction ordered halted on natural gas pipeline

(KOLNKGIN)
Published: Mar. 13, 2018 at 6:47 PM EDT
Email This Link
Share on Pinterest
Share on LinkedIn

A company building a 713-mile-long natural gas pipeline has been ordered to halt construction after West Virginia inspectors cited 14 violations.

the offenses include leaving trash and construction debris partially buried on site, improperly installing perimeter control and failing to inspect or clean public and private roads around the construction site.

The Rover Pipeline, owned by Energy Transfer Partners, would transport 3.25 billion cubic feet of natural gas per day from processing plants in West Virginia, Ohio and Pennsylvania.

Rover Pipeline and Energy Transfer Partners spokeswoman Alexis Daniel says they are working with federal and state officials to resolve concerns.

The cease-and-desist order was sent March 5 from Scott Mandirola, director of the West Virginia Division of Water and Waste Management.